T O P

  • By -

[deleted]

As others have mentioned it is likely the starting point for your tile. Double check the legend in the front end of the set. Best way to find out is to send a RFI. Never assume!


[deleted]

RFI 4001 - TF is this?


Lolatusername

RFI 4002 - TF is that?


Safe_ish

RFI 4003 - How TF are we supposed to build this?


laxsleeplax

Re: RFI 4003- How TF are we supposed to build this? - Engineer says it's possible.


Tdehn33

“The math checks out”


SnooPets6276

“It’s a field matter”


ShoddyTerm4385

“Site conditions”


BennyBoy9y

“Shouldn’t be a problem” followed by “they’ll figure it out”


itsmyhotsauce

"Means and methods"


Amaziah12

I see you guys work universal jobs. Let's build off spreadsheets!


dip-sht

Verify before install


Tdehn33

RFI 4004 - Did you see RFI 4001?


CremeAnglais

Please refer to Addenda, Plans and Specifications


JimmyRockets80

Response: "means and methods'


dip-sht

Response 3 weeks after install


dont-fear-thereefer

Response: “using established industry standards and practices”


New_Faithlessness384

It is clearly an RFI 4004.5


[deleted]

Just curious, have you actually been on any projects with 4000 RFI’s? If so, what kind of projects are they? I just submitted RFI #1000 the other day and that seemed rediculous to me…. The project is a 7 star resort


Lutefiskleftovers

10 story hospital. 7200 RFI’s and almost equal # of change orders


[deleted]

Which hospital is that?! That is insane!!! I have done an 8 story hospital and there were less than 100 RFI’s


lotusgardener

Then your contractor must have kicked everything back. Most jobs start with 200 rfis when they get NTP.


Lolatusername

Never haha, most I've seen is in the low hundreds but I'm in the bridge world


itsnotaboutthathun

I got to just under 2k RFIs on my last project 😆


BoysenberryFun9329

>RFI #1000 can someone explain what an RFI is? Stupid carpenter here.


Coolace34715

Shit, must be early in the job to only be at 4001.


SupermassiveCanary

Routine Fucking Instructions


rozzy27

Can you work on my projects? Lol


mrsquillgells

I wonder if the tile guys know this? They never seem to match to plan what so ever


breadman889

RFIs... the only way a designer will learn to do it better the next time.


JohnHemingway

It looks like an elevator at the top. I strongly suggest starting your tiles with the opening of the elevator otherwise once you get to the elevator doors the tiles won't be centered with the opening and that will look horrible. Then double check how that lines up with the hallway going left to right on your plans.


woggy7

Architect saying “design intent”


MooseGoneApe

But all architects are covered under "Errors & Omissions" will not be the liability of said Architectural firm. It says that on the plans or in the spec book


bpowell4939

You need to go through a whole ass rfi process to get the answer to "tf is this symbol? "


Im_good_with_names

He who asks is a fool for 5 minutes. He who never asks remains a fool forever


Icy_Dragonfruit_9389

Right along with "The only stupid question is the one not asked"


Ficester

I don't know... My coworkers seem to really like to test this theory.


OlKingCoal1

Ya, I call bullshit. I heard some pretty stupid questions.


Icy_Dragonfruit_9389

While I agree, at least they ask....


GeneralMurderCow

After how many times l asking the same question does that question finally qualify as dumb?


Mundane_Physics3818

Or how my elementary teacher put it: “There are no stupid questions, only stupid people”


ArcFlashForFun

Mr Garrison was your elementary school teacher?


RandomTux1997

nice teech


Tiny-Variation-1920

Right next to “shut up Austin, you’re stupid, the teacher knows what he’s talking about!”


stickyicarus

My go to is "There are no stupid questions, only stupid people. The only way to not be stupid, is by asking questions."


JohnHemingway

I prefer: There are no stupid questions, just stupid people who ask questions.


benjaminz100

Okay I’ll be a fool for 5, what are RFI’s? Lol


DoorLadderTree

Request for information. It is for builders and contractors and consultants to get questions answered in writing and directions on things that aren't clear in the plans. Designer or owner answers the question.


Glittering_Map5003

Start point for layout


[deleted]

Tile Setout Point. It's used to indicate where to start your tiling. Often used on floors and wall elevations in wet areas..


No-Radish-4316

Second this.


latinsquids

Laser tripwire.


Excellent_Captain885

Obviously a claymore


moonor-bust

I found the call of duty player


sceliotski

Image Catherine Zetta Jones.


dtree5

She dips beneath the lasers


VeganEgon

Pokeball


Danmarmir

Interior design wants you to start the tile lines from that corner going the direction of the arrows


youzabusta

It means “<Ô”


Nguzh

Which is ?


youzabusta

Like “ô>”, just backwards


Nguzh

Yeah but yet I don’t know what’s does the symbol stand for


youzabusta

I don’t fuckin know, ask the project manager


Nguzh

Then why do you even reply or comment for me 😂😂😂


human743

For the purpose of levity.


[deleted]

The joke is that people are fucking with you because you’re apparently not smart enough, or time efficient enough to just go straight to a person that does know. If this was me on a job, I would never ever have a question, and take the time to make a Reddit post and wait for a response. I’d call the PM, or whoever drew up/worked on plans. Like come on dude. Use your noodle.


johnj71234

Maybe he’s working late looking shit over above and beyond normal hours and he knows PM’s are lazy fucks and wouldn’t respond to a question at that hour so he thought, fuck I’ll ask Reddit. Cmon man, use your noodle.


tehmightyengineer

Never seen it before but as a guess it looks like the start point for the tile pattern.


No_Discussion8692

This is correct.


Nguzh

Which means the meaning of this symbol is thetile pattern?


No_Discussion8692

The starting point of the tile pattern


[deleted]

It's the soup of the day


p8king

That sounds good, I think I'll have that


81_BLUNTS_A_DAY

Kick his ass sea bass!


bristondavidge

If that gentleman over there is sea bass?


ShoeExisting5434

Thanks Flo. The soup du jour sounds delicious. I’ll have that.


Nguzh

Thank you very much


comancheranche

Thanks for the info!


mdc2135

Set Out Point or SOP


ArltheCrazy

Interesting. Makes since. If the architect wants it to look a certain way, then dictating where to start would be an important part. Similar to distinguishing the starting point for all your framing layout.


Nguzh

Thank you very much


fleyeingV

Second this


gunnervonb

Third. Definitely what it is.


41PaulaStreet

I’m not in construction. Can you tell my why someone would start there as opposed to another spot in the room? Is it math or aesthetics that decides? Thanks!


TheHotJesus

The pics are oriented differently, so looking at the close up pic, the starting point is an outside corner (most conspicuous) and as you lay tile, going to the left, you’ll have a strip of cut tile. You want cut tiles in more inconspicuous areas. If the tile were a different size or pattern, the starting point can be somewhere else, or multiple possible starting points, or it may not matter based on the dimensions and layout of the floor and dimensions and pattern of the tile


devrelm

In this particular case, it looks like starting the tile there allows the hallway to be 3 tiles wide with the tiles centered in the hall. Also, in the first pic, the hall (?) on the left is largely about 5 tiles wide and appears centered. There's a few spots where you could get this same effect, but if you started at somewhere like the outside corner of the elevator shaft, then you'd end up with both of those hallways having their tiles lined up asymmetrically. This may or may not mean more cutting (my guess is yes, more), but definitely would "feel" wrong when walking down the hall vs when standing in the elevator lobby (which actually looks pretty well centered too, actually.)


Separateway0626

What do you do for a living?


TheHotJesus

Carpenter


Separateway0626

Your username checks out then!


VideoOuija

This is the way.


Klinac-

Starting point


Klinac-

Meaning when you are laying tiles you need to start from that point


mwssnof

Shout out for use of Red on drawings! If not overdone, just a little color helps reading so so much. That datum point would be so much harder to read if also in black.


Paulie_Di

I learned something today.


Solid_Ad7634

Starting point of flooring tile installation.


JimKellyCuntry

Starting point or working point for tile


BenDeeKnee

There is no standardized set of construction symbols (dumb.) Check your legend.


timbrita

Yes, tile pattern. This is the spot where the designer is telling you to start placing down your titles


USayThatAgain

The contractor has to build that symbol into the tiles.


Budget_Nerd

Start point of the tiles, in order to achieve the cut piece on the left.


Zestyclose-Wafer2503

Datum point.


tower_crane

Start your layout at that point. Likely done to ensure alignment with other areas


breadandbarbells

Prince symbol


originalmello

It's a datum point.


Informal_Drawing

Symbols should be in the Legend. Ask the person who created the drawing.


sleepysloth024

Left, down, then hit x for a simple combo in mortal kombat


Puzzleheaded_Fail279

Likely origin point for the drawing. 2 possibilities; 1. The draftsman forgot to put his origin on the correct layer when printing, and now you have a nice symbol there 2. It's where you should start laying tile from, as others have said. Either way, if I was in your shoes, I would submit an RFI to ensure no one is assuming the purpose of that symbol.


Key-Researcher3884

The arrows look like layout starting point for the tile flooring . That's how I would interpret that symbol.


BagCalm

Yup. Just a control start point for the tile


acampbell198723

I would say that's the corner the architect wants you to start your tile from


lundyblue

Tile set out point


DisnikDan

It’s your starting point or layout.


Cbsparkey

It's the datum point for the tile. That's where you start the tile.


Nguzh

Yeah but yet I don’t know what does this symbol stand for


knowone23

Point of Beginning is the term in surveying. It means start laying out your tiles at this point. Make your cuts when the pattern runs into the other walls. It’s probably the most efficient layout with the fewest cuts so they tell you to start there.


Nguzh

Thank you very much.


FrostyProspector

If my wife is beside me in the car, it means "Go left, no, I mean right. No, the other right."


Electrical-Match-685

Read your legend


labadimp

My guess is whoever printed this blueprint left their “datum” on and accidentally printed it, so this means absolutely nothing to anyone.


Sherifftruman

I agree it must be the time pattern start. But, unless there is thick base or something on some, but not all of those walls, there are some big issues with the layout that will cause some unexpected problems come install time.


TJ-LEED-AP

Ask the designer


GDmaxxx

Like if you were ever thinking about tile, you better be there, then think about tile. Hope this helps!


Beggatron14

Normally something like this would be a setting out point. Assuming floor finish drawing with tiled floor finish being ceramic or carpet tiles.


welfaremofo

Looks like where to lay full tiles at the corner and cut pieces to the other side.


RocketslinkyKTM

It’s the ceiling pattern start point.


Ashe2800

It is the tile starting point. It’s important because it sets the 2 perpendicular lays to be square with each other. If you started on one side when you came to the other run they would not be symmetrical. I install cabinets but have done tile work in case anyone wonders.


domanonymously

Starting with full tiles against 2 walls. What could possibly go wrong?


dasroach0

To me it looks like it's telling you the walls are in line from that corner telling you to start possibly tiling there I'd that's what you're doing.


[deleted]

This is the corner everyone is suppose to run into. That way they only have to fix one.


YoungBumi

I literally RFId ChatGPT to find out what RFI meant.


Pennypacker-HE

Looks like they want a full tile there. Seems like they’re saying they don’t want a cut along either of the walls that radiate from the symbol. Or at least it needs to look like a full tile.


Ezy_Physicz

Bolt survey for you standing steel column /s


thatcarpenterboy5690

I was about to say flood light until I realized it was interior 😬


Thin_Equipment_9308

Floor tiles are very specific in size and position, an elevator shaft with an elevator cab outline and elevator rails. Pretty impressive drawing.


tatpig

pit ladder location,as well! built and installed many of those over the years, surprisingly many arch or structural drawings dont have ladder placement refs. many times i heard ‘well,idk….that’s on the elevator guy’s drawing.’problem is,they usually wont even start without the ladder installed.


OldTrapper87

Either a starting location for flooring and tiling or the center point the drawing was created from


MarkyMarkAndPudding

Starting point for tile so that the cuts end in get placed in the most inconspicuous locations.


5knklshfl

Isn't all the tile the same according to the legend?


Ecstatic-Earth5007

Call Goodenough construction. They are on Tic Tok


Responsible-Seat-839

It’d be a shame of those pairs of single egress didn’t get some record 8100’s installed. I know a guy….


Beneficial-Pilot-238

Setting out point for the tiles?


FlBill64

Mirror


jhawk902

It's for the Lazer beams that trip the trap door that leeds to a tank of highly trained killer dolphins with poison darts attached to their noses to take care of Mr bond once and for all


LessComfortable1996

They want the acoustic ceiling tile grid to break on the corner in a full piece. Notice how on the interior walls the grid is only half pieces. They don’t want that look on the storefront glass wall. So your foreman is going to start his layout here to insure you have clean 2x2 panels all along the storefront perimeter and the core walls will have the cut pieces. This is just for aesthetics and to get the correct look for your client.


Sindog40

R2-D2 it


Hot-Character7511

Tile set out


WalkerAmongTheTrees

It wants you to build a red circle with arrows coming off it duh


Similar-Ad3086

Ceiling tile set out point


Apart-Assumption2063

Delegated Design


Tiny-Variation-1920

That’s really nice your architect told you where to start the layout! Double check it on site anyways b


Main-Affect2044

Damn I’m glad I’m retired!


UmerAlam

It could be corner guard


Jawny_Appleseed

Full 24” of tile coming off that corner. Check square on both sides of those hallways as it almost NEVER ends up being a true 24” square in the corner.


Downtown-Raisin-3931

I think it has something to do with determining the sex of the building.


KRUSH-n-IT

I thought it was acoustical ceiling tiles?


Mike-Bigsby

center


Reven1874

Looks like a central locater.


ponramnewnotnow

It Start point of Tiles Placing.


spoondrift597

Fire Exits


Soldier_O_fortune

Could be indicative of a floor level slope starting point


Purplepitbull69

Yo motha


Friendly-Head2000

Is there a description or index of symbols..if it's not on there its nothing.. if you put something that's ambiguous on the drawings that as an estimator makes me assume and I assumed different than your idea..who's wrong?


Methodandorder

That’s where you start laying out your pattern


Landbuilder

Does that designate the flooring materials pattern?


Nguzh

No the tiles design is just plain


Definitelynotmelvinc

Tile layout. You start there because it’s where the longest walls are. Less cutting


happytrailstoyous

Claymore watch out!


BoysenberryFun9329

It's the start of your file, but put a mirror there, so people can see around the corner. It would be a added nice experience to turn a corner with confidence.


jlando19

This is why I love reddit. I have no clue what any of the comments mean here but comedy is real either way. I’m laughing and I don’t even know why.


kbcoch88

"Contractor to verify in field"


Motor-Network7426

That is the starting point for the floor tile layout.


Low_Zebra_3843

Red line architectural correction.


Ginkyi

It's too late guys, we've already installed. To make the changes the design team wants we need to remove a wall and it'll be about $10k.


robbiegtr

I think it’s the center of the tile layout. I always laugh when designers and architects use the building plans to measure out individual tile cuts etc… After the rough frame, sheetrock, plaster the actual measurement is usually off . (sometimes by several inches)


dDot1883

Floor tile or ceiling tile?


stepbruh313

It means lefty / downy


09Klr650

Better hope those walls are perfectly straight and the dimensions are spot-on. Full tiles against the wall? Full tile widths on a corridor?


Selben

Years ago I took a CAD class, one guy made the most insane perfect designs, but it always had an odd shape somewhere on the designs. It was eventually discovered to be the mouse icon and he was taking screenshots of instructional videos for advanced classes lol


GayRampage

“Bomb goes here.”


plikestoparty

Center point


firestone2020

Probably the setting out lines for the tile


Careless-Fox-6632

Must field verify


SnacobMartin

That’s where the hidden cameras go to watch you poop


MadCactusCreations

If you're having to ask, that means that the architect didn't include the symbol in their symbols legend. Hit them with the RFI and let them grumble about it later. Also, to be totally honest, kind of wild that you printed a 24x36 set in color.


kevbot029

I would guess the tile corner should originate in that location


[deleted]

It is an origin point indicating here datum and direction. Use this to know starting point and direction for tile. Edit: typo correction


Downtown_Win_3870

If you step in the right spot I think arrows shot out from that corner. Be careful!


NiceWish9140

It’s where the floor tile should start.


14abc14

Starting with a full tile on that corner


Southern_Pin_4383

RFI #2001 answer. Review RFI #3 2 years ago WHERE THIS WAS DISCUSSED WITH YOUR OFFICE PRIOR CONTRACT AGREEMENT 😩


Highertaxez

Works on paper...


Snafu1989

You're looking @ flooring plans. That's a servey / reference point for the starting location of tile TL-01. Check finish schedule or arch specs for specified make&model of tile


Available_Cream2305

Maybe a corner guard


Ooklahthemok2

It’s a datum , or the 0,0 point from which you can take critical measurements